Maharashtra GCC policy: status, incentives and targets

Quick answer

The Maharashtra GCC policy 2025 is a state policy that offers fiscal and non-fiscal incentives to new global capability centres (GCCs). According to The Week (2025), the state cabinet approved it on 30 September 2025, with a target of 400 new GCCs and 4 lakh (400,000) jobs between 2025 and 2030.

The cabinet approved the policy on 30 September 2025, and a later report says its operational guidelines were notified by government resolution in August 2026. We found no source for the date of the original resolution. CapSight tracks 2,544 GCCs across India (as of November 2026); the policy facts below come from named public sources.

What is the Maharashtra GCC policy?

It is Maharashtra’s plan to attract new GCCs, with zone-based incentives tied to the investment a centre makes. According to Nexdigm (2025), the consultancy’s note says the policy stays in effect for five years, until FY 2029-30. It lists capital subsidy or rental assistance, payroll subsidy, interest subsidy, power tariff subsidy and stamp duty exemption among the fiscal incentives. The same note lists industry status, extra floor space index, reserved MIDC land and priority allotment as non-fiscal ones.

What is the policy’s current status?

The policy was cabinet-approved on 30 September 2025, and NewKerala reported on 20 August 2026 that its operational guidelines were notified by government resolution. According to The Week (2025), the cabinet cleared the policy on that date. According to Nexdigm (2025), the state had issued it by 14 November 2025.

According to NewKerala (2026), a government resolution approved and notified the operational guidelines and standard operating procedures. The report is dated 20 August 2026 and says the resolution was issued on a Wednesday. We found no source that gives the date or number of the original resolution. We did not open the policy text, which is reported to be hosted by MIDC, so all terms below are as reported by others.

What does the policy target?

The policy sets targets, not results. According to The Week (2025), it is expected to attract Rs 50,600 crore of investment and generate 4 lakh jobs between 2025 and 2030. According to The Week (2025), another 400 GCCs are to be established, and the report names Nashik, Nagpur and Chhatrapati Sambhajinagar as locations for expansion.

According to NewKerala (2026), the chief minister set targets of 400 new GCCs, 400,000 high-skilled jobs and Rs 50,000 crore of investment on 11 August 2026. The two investment figures come from different reports, so we keep them apart.

What incentives does the Maharashtra GCC policy offer?

The incentives are zone-based and tied to the size of the investment. All terms below are as reported by NewKerala (2026), which summarises the guidelines resolution and not the policy text. Check the resolution before you rely on a term.

According to NewKerala (2026), Zone I covers the Mumbai Metropolitan Region and the Pune Metropolitan Region, and Zone II covers the rest of the state. It reports a capital subsidy of up to 20% on plant and machinery investment made after 1 April 2025. According to the same NewKerala report (2026), the caps run from Rs 10 crore for small units to Rs 100 crore for mega units, in five equal yearly instalments.

According to the same NewKerala report (2026), the rental subsidy is 10% in Zone I and 20% in Zone II, and it cannot be combined with the capital subsidy. It also lists a three-year payroll subsidy and a full electricity duty waiver for 10 years. According to NewKerala (2026), stamp duty exemption is 100% in Zone II IT parks, SEZs and STPI units, and 75% in Zone I public IT parks.

Which centres qualify, and how are they tiered?

Only captive centres of multinational or Indian global groups qualify, and the tier depends on investment and jobs. According to NewKerala (2026), call centres, BPO units and pure sales entities are excluded. Nexdigm (2025) gives the same exclusions.

According to NewKerala (2026), a small centre invests Rs 50 to 100 crore and creates 250 to 500 jobs within two years of starting operations. According to the same NewKerala report (2026), a mega centre invests Rs 500 to 750 crore and creates 1,000 or more jobs. Medium, large and ultra mega tiers sit between and above these. It also reports that benefiting units must stay operational for at least 10 years.

How does Maharashtra’s policy compare with Karnataka’s?

Both states have a cabinet-level GCC policy with its own targets, and each is described by different sources. Our page on the Karnataka GCC policy sets out that state’s dates and terms. We do not compare the two sets of figures, because the sources, definitions and years differ.

For location detail, see our guides to GCCs in Pune and GCCs in Mumbai.

What should a GCC leader check before relying on the policy?

Check the resolution text, your zone and your tier. The summaries above do not give every eligibility rule. Confirm which zone your site falls in, the investment and job thresholds for your tier, and which incentives are being paid today.

Ask the state’s industries department for the current guidelines. Our page on GCC setup cost in India covers the other costs to plan for.

CapSight data

CapSight counts about 590,000 people working in GCCs in Maharashtra (as of 30 Sep 2026).

GroupPeopleShare
Technologyabout 240,00041%
Finance & Accountingabout 78,00013%
Strategy, Consulting & Program Managementabout 76,00013%
Engineeringabout 47,0008%
Sales & Marketingabout 30,0005%
OtherShown as a share20%

Source: CapSight GCC database, among the GCCs CapSight tracks

As of: 30 September 2026

Rebuilt as of 30 Sep 2026: jobs that started after that date are removed. People who left after 30 Sep 2026 cannot be added back, so this is close to, not exactly, the count on that day. Figures are rounded. Not covered: every employer in India; CapSight tracks a defined list of GCCs.

The cut counts people with a current job in the GCCs CapSight tracks, not every employer in Maharashtra.

Conclusion

The Maharashtra GCC policy 2025 was cabinet-approved on 30 September 2025, and NewKerala reported on 20 August 2026 that its operational guidelines were notified by government resolution. Treat reported terms as leads. Confirm your zone, tier and incentives against the resolution before you build a business case.

Frequently asked questions

What is the Maharashtra GCC policy?

It is Maharashtra’s policy for new global capability centres, valid for five years until FY 2029-30, according to Nexdigm (2025). According to The Week (2025), it targets 400 new GCCs and 4 lakh jobs between 2025 and 2030.

Is there a Maharashtra GCC policy for 2026?

We found no new Maharashtra GCC policy for 2026. According to NewKerala (2026), a resolution reported on 20 August 2026 approved operational guidelines for the 2025 policy. Check the state industries department for any later order.

Where can I find the Maharashtra GCC policy PDF?

We did not open the policy PDF, so we cannot confirm where the official copy sits. The policy text is reported to be hosted on the MIDC website. Search there, or ask the state industries department, and confirm the resolution number and date on the document.

Do GCCs outside Mumbai and Pune qualify?

Yes, and they sit in a different zone. According to NewKerala (2026), Zone I is the Mumbai and Pune metropolitan regions and Zone II is the rest of Maharashtra. It reports a higher rental subsidy rate of 20% in Zone II, against 10% in Zone I.

Which jobs does the Maharashtra GCC policy count?

The sources give a job target, not a counting rule. According to The Week (2025), the target is 4 lakh jobs between 2025 and 2030. According to NewKerala (2026), each tier has a job threshold within two years of starting operations.

About CapSight: CapSight tracks 2,544 GCCs in India and the 3.41M people who work in them (as of November 2026).